Dashboard 07 — Statutory Approval Tracking
MTR C1604 · AP Architect View · BD / FSD / EMSD / Lands / MTR
AP: John Smith · Updated: 2026-07-17 14:30 HKT
Live
📦 Total Packages
14
BD: 5 · FSD: 4 · EMSD: 3 · Lands: 1 · MTR: 1
All Tracked
⏳ Pending
3
FSD: 2 · EMSD: 1
Action Required
⚠️ Overdue
1
FSD-004 · 3 days late
🔴 Urgent
✅ Approved
10
71% approval rate · Avg 11 days
On Track
📊 Submission Pipeline
14 packages · Click card to view details
📋 Submission Package Register (14 packages)
Package Authority Title / Zone Submitted SLA Docs Status
Showing 1–10 of 14
🚨 Urgent Actions
3 items

FSD-004 OVERDUE — 3 Days Late

Missing: Shop drawings (2 files) · Fire alarm Zone 3-A
Action: Request from M&E contractor by EOD today

BD-005 Due in 3 Days

Structural Zone 1-B · Auto-reminder sent to consultant
Completeness: 95% · 1 calc sheet missing

MTR-001 Draft — 15 Days Old

Platform design package · Ready to submit
Awaiting AP signature · All docs complete
📊 Approval Rate by Authority
📈 Avg Approval Time (Days)
Target ≤14 days
🤖 AI Document Completeness
Last scan: 14:00 HKT
11Complete
3Incomplete
187Total Docs
Missing Items Detected
FSD-004: Shop drawings (2 files)CRITICAL
BD-005: Structural calc sheetHIGH
MTR-001: AP signature pendingMEDIUM
All other 11 packages completeOK